Binagadi, Boyuk-Shor Lake, Muzaffar Narimanov Project

Duration:

September, 2012 - January, 2016

Project Description:

Construction of steel water pipeline in Binagadi district; reconstruction of steel water pipeline around Boyuk-Shor Lake; construction of steel water pipeline on Muzaffar Narimanov Avenue in the city of Baku

 

Project Location:

Azerbaijan

 

Contract Value:

70.000.000 USD

 

Employer:

“Azersu” Open Joint Stock Company

 

Binagadi Steel Pipelines:

Project Description:

Construction of potable steel water pipeline and connection to a water reservoir at +82 level

 

Project Details:

Construction of steel pipelines:

  •  Diameter – 1420 mm; Length – 531 m
  •  Diameter – 1620 mm; Length – 534 m

 

Boyuk-Shor Lake Water Pipeline

Project Description:

Reconstruction of steel water pipeline around the lake of Boyuk-Shor

 

Project Details:
Excavation works – 486000 m3
Construction of pipelines:

  •  Diameter – 160 mm; Length – 654 m
  •  Diameter – 400 mm; Length – 402 m
  •  Diameter – 1420 mm; Length – 3435 m
  •  Diameter – 1620 mm; Length – 3611 m
  •  Diameter – 2020 mm; Length – 204 m
  •  Diameter – 2300 mm; Length – 50 m

 

Steel Pipeline On Muzaffar Narimanov Avenue

Project Description:

Construction of potable steel water pipeline on Muzaffar Narimanov avenue/Baku.

 

Project Details:
Construction of pipelines:

  • Diameter – 1420mm; Length – 2032m
  • Diameter – 1620mm; Length – 53m