Water Supply To Gala Settlement Phase 1 – Water Reservoir Construction

Duration:

October, 2012 - May, 2014

Project Description:

Construction of a water supply and sewerage system and a water reservoir

 

Project Location:

Azerbaijan

 

Contract Value:

13.334.000 USD

 

Employer:

“Azersu” Open Joint Stock Company

 

Project Details:

Construction of polyethylene pipelines:

  • Diameter 32 – 160mm; Length – 15339 m
  • Diameter 250 mm; Length – 1540 m

Construction of corrugated pipelines:

  • Diameter 150-600; Length 12054 m

Construction of a water reservoir:

  • 10000 m 3