Water Supply To Gala Settlement Phase 1 – Water Reservoir Construction
Duration:
October, 2012 - May, 2014Project Description:
Construction of a water supply and sewerage system and a water reservoir
Project Location:
Azerbaijan
Contract Value:
13.334.000 USD
Employer:
“Azersu” Open Joint Stock Company
Project Details:
Construction of polyethylene pipelines:
- Diameter 32 – 160mm; Length – 15339 m
- Diameter 250 mm; Length – 1540 m
Construction of corrugated pipelines:
- Diameter 150-600; Length 12054 m
Construction of a water reservoir:
- 10000 m 3